North Beach Access Road Project July Update

 
NBAR_7.15.19d
© 

The project is going very well, on time and within budget, thanks to many donors who contributed to this important public-private partnership.

  • 25,000 cubic yards of stone were used to build the new "bluff"
  • 500 linear feet of drain piping was installed near the top of the existing slope
  • 600 linear feet of sanitary pipe was installed under the new road

Through September, the project will involve:

  • Installing a new storm sewer connection
  • Final grading of the embankment and installing topsoil
  • Paving the parking lot
  • Installing the concrete road, curb and new wooden guard rail

Concurrently, the City is working on the ravine restoration to the immediate north of the North Beach Access Road.

Updates are provided at each City Council meeting, which are held on the first and third Mondays of the month.  You may livestream meetings or view them on the City's YouTube channel, EnjoyLakeForest.

NBAR_7.15.19c

 

Back

 

THE CITY OF LAKE FOREST
220 E. Deerpath, Lake Forest, IL 60045
(847) 234-2600
Non-Emergency Police:  (847) 234-2601

close (X)